Another tough break for Bertha. Further delays are expected for the giant tunnel machine and Seattle’s viaduct project.

The Washington State Department of Transportation told the Seattle City Council Monday that damage to Bertha will delay its progress further.

“Even though the damage is more than they were expecting to find, it’s not more than they were planning to repair at this point,” said Todd Trepanier with WSDOT.

For example, WSDOT said the outer seals and the steel retainers that hold them in place were destroyed. There was also damage to the cutter drive motor pinions and the main bearing bull gear.

Minor damage also occurred during disassembly.

Crews have also decided to replace the inner seals to make them more compatible with the new outer seals and main bearing. Those new seals have to be manufactured in Japan and won’t arrive until late May.

It is up to the Seattle Tunnel partners as to how long the project will be delayed.

So who’s going to pay for all this? WSDOT said STP and Hitachi are responsible for all aspects of the repair effort. WSDOT tells KIRO Radio’s Josh Kerns a dispute resolution is far down the road and it’s not a priority right now.

In addition to the damage, WSDOT told the City Council there are no simple answers as to why the ground near the SR 99 tunnel access pit settled about an inch last November.

One report, done by geotechnical firm Shannon & Wilson, Inc. and commissioned by WSDOT, said that dewatering related to tunneling machine repairs was the primary cause of the settlement.

A second report, concluded by Brierley Associates and commissioned by Seattle Tunnel Partners, said natural settlement and other dewatering activities are the primary reasons for the settlement, and tunnel-related dewatering only contributed in areas immediately surrounding the pit.

While the reports may differ slightly, they both conclude that settling related to dewatering has since stabilized, and ground movement was minor and caused no structural damage.

Richard D. Oxley contributed to this report

MyNorthwest News

Image: A burner on a stove emits blue flames from natural gas in Des Plaines, Illinois in 2005....

Matt Markovich

Signature gathering begins for initiative to keep natural gas in Washington

Those seeking to halt the state's efforts to eliminate natural gas use in homes and buildings want to get the measure on the November ballot.

2 hours ago

Photo: Tacoma City Council member Catherine Ushka has died after a battle with cancer. She represen...

Julia Dallas

Tacoma city council member dies after battle with cancer

Tacoma City Council member Catherine Ushka has died after a battle with cancer. She represented District 4.

6 hours ago

Image: Interstate 5 North in Everett at US 2 was completely blocked due to police activity incident...

Steve Coogan

I-5 north in Everett is fully blocked after an officer-involved shooting

Interstate 5 north in Everett at US 2 is closed after an officer-involved shooting, a state law enforcement agency reported Thursday night.

6 hours ago

Photo: Seattle Times publisher and CEO Frank Blethen announced he will step down at the end of next...

Associated Press

Seattle Times CEO to step down after 4 decades in charge of family-owned paper

Seattle Times publisher and CEO Frank Blethen announced he will step down at the end of next year after four decades of leading the paper.

8 hours ago

Photo: Yelm High School students staged a school walkout Wednesday. Students said they did it to fi...

Gwen Baumgardner, KIRO 7 News

‘Our education out here is going to crumble:’ Yelm students walkout after teachers get layoff notices

Yelm High School students staged a school walkout Wednesday. Students said they did it to fight for their teachers and their education.

9 hours ago

Photo: A sign is posted outside of The North Face store on March 07, 2024....

Julia Dallas

North Face closes downtown Seattle flagship store

The North Face has closed its downtown Seattle store. The store operated at 520 Pike Street for nearly five years.

11 hours ago

More delays for Bertha, viaduct project